CASE STUDY • INGREDIENTS MANUFACTURING
Reinforced for Harsh Detergents and Constant Traffic.
Ingredients Manufacturing Facility — Ravenna, Nebraska
About This Project
Old, failing concrete and a deteriorating epoxy floor system had exposed aggregate across critical production areas at an ingredients manufacturing facility in Ravenna, Nebraska. The compromised surface created slip-and-fall concerns, made sanitation more difficult, and put GMP and FDA expectations at risk. The facility needed a durable replacement built for harsh detergents and constant vehicular traffic.
Tufco installed 4,500 sq ft of Tufcrete reinforced with expanded metal — installed by our own crews with all work completed in 72 days. No drain work was required.
The Solution
Tufco’s own W-2 crews — no subcontractors, no “certified installers” — prepared the failing substrate, placed expanded-metal reinforcement across the installation area, and installed 4,500 sq ft of Tufcrete. The reinforced system was selected to deliver added strength across an active manufacturing floor exposed to repeated cleaning and traffic.
The result is an impervious, seamless floor that holds up to the harshest detergents and constant vehicular traffic — reinforced with expanded metal to support long-term performance. The finished surface improves footing, simplifies sanitation, and supports GMP and FDA compliance. All work was completed in 72 days, start to finish.
One crew. One warranty. Zero excuses.
5 YEAR WARRANTY
Installed exclusively by Tufco employees. No subcontractors. Ever.
Every installation is backed by an industry-leading 5-year warranty on both materials and workmanship. No fine print. No exceptions.
Your floor is telling you it’s time. Don’t wait for the audit.
uilt for the harshest environments — backed by a 5-year warranty. See what Tufco can do for your facility.
Project Installation & Result
APPLICATION OVERVIEW
LOCATION
Ravenna, Nebraska
CLIENT
Ingredients Manufacturing Facility
Name withheld at client’s request
INDUSTRY
Food & Ingredients Manufacturing
SYSTEMS
Tufcrete with Expanded-Metal Reinforcement
4,500 sq ft installed · No drain work
SCHEDULE
All work completed in 72 days
Start to finish
WARRANTY
5 Years — Materials & Workmanship